Jin Xiangjin (middle in front) and others visit the project site
At 830 am, Feb. 2nd, along with the sound of fireworkers, the 1st phase of engine casting transformation project of
The project began the exchanges of processing equipment and technological and bidding work in April, 2008. In order to save time, the project department and other Designing Institute worked hard on the project. The main workshop of the 1st phase started construction on February 15 2009. It was 13 days ahead of schedule. According to the time frame for the project, the main workshop is due to be completed within 390 days.
The 1st phase of the project consists of the No.1 casting workshop, warehouse and other necessary supporting facilities. The construction of the
The casting center project started in October 2007. Its technological level was set to achieve the domestic leading position. The technique and equipment were to meet the domestic first-class level.
Author: Zhou Qinxu photographer: Ning Jing